— Project Summary

Queue ID
BPA-G0937
Capacity
117 MW
Technology
Solar
Status
active
Location
Wasco, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

117 MW generation in Wasco, OR · In queue since September 2023 · Proposed COD October 2025

117 MW

Capacity

1

Components

Solar

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 1m

Schedule

6 months past proposed COD

In Study38%
Queue EntrySep 18, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-10-01

Project Details

State

OR

County

Wasco

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Chemoweth Substation; Alternates: Quenett Creek Substation & Chenoweth-Goldendale No 1 115kV line.

Data Source

LBNL

No news available for this project.