BetaActiveSolarBPALBNL
117 MW generation in Wasco, OR · In queue since September 2023 · Proposed COD October 2025
117 MW
Capacity
1
Components
Solar
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 1m
Schedule
6 months past proposed COD
In Study38%
Queue EntrySep 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-10-01
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Chemoweth Substation; Alternates: Quenett Creek Substation & Chenoweth-Goldendale No 1 115kV line.
Data Source
LBNL
No news available for this project.