BetaActiveWindBPALBNL
150 MW generation in Klickitat, WA · In queue since September 2023 · Proposed COD September 2025
150 MW
Capacity
1
Components
Wind
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2 years
Schedule
7 months past proposed COD
In Study38%
Queue EntrySep 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-01
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Rock Creek Substation
Data Source
LBNL
No news available for this project.