BetaActiveSolarBatteryBPALBNL
1,000 MW hybrid in Sherman, OR · In queue since September 2023 · Proposed COD December 2028
1,000 MW
Capacity
2
Components
Solar + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 3m
In Study38%
Queue EntrySep 7, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Technology
Solar500 MW · 50%
Battery500 MW · 50%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Buckley Substation
Data Source
LBNL
No news available for this project.