— Project Summary

Queue ID
BPA-G0923
Capacity
300 MW
Technology
Solar+Battery
Status
active
Location
Walla Walla, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWindBatteryBPALBNL

300 MW hybrid in Walla Walla, WA · In queue since September 2023 · Proposed COD September 2027

300 MW

Capacity

3

Components

Solar + Wind + Battery

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntrySep 5, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-09-15

Technology
Solar100 MW · 33%
Wind100 MW · 33%
Battery100 MW · 33%
Project Details

State

WA

County

Walla Walla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Lower Monumental _x0013_ Little Goose No 1 500 kV line. Alternates: Lower Monumental _x0013_ Little Goose No 2 500 kV line; Little Goose _x0013_ Central Ferry No 2 500 kV line

Data Source

LBNL

No news available for this project.