BetaActiveWindBatteryBPALBNL
600 MW hybrid in Thurston, WA · In queue since September 2023 · Proposed COD October 2030
600 MW
Capacity
2
Components
Wind + Battery
2y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 1m
In Study38%
Queue EntrySep 1, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-10-30
Technology
Wind300 MW · 50%
Battery300 MW · 50%
Project Details
State
WA
County
Thurston
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Chehalis - Covington No 1 230kV line.
Data Source
LBNL