— Project Summary

Queue ID
BPA-G0921
Capacity
600 MW
Technology
Wind+Battery
Status
active
Location
Thurston, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBatteryBPALBNL

600 MW hybrid in Thurston, WA · In queue since September 2023 · Proposed COD October 2030

600 MW

Capacity

2

Components

Wind + Battery

2y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 1m

In Study38%
Queue EntrySep 1, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-10-30

Technology
Wind300 MW · 50%
Battery300 MW · 50%
Project Details

State

WA

County

Thurston

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Chehalis - Covington No 1 230kV line.

Data Source

LBNL

No news available for this project.