— Project Summary

Queue ID
BPA-G0920
Capacity
800 MW
Technology
Solar+Battery
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

800 MW hybrid in Benton, WA · In queue since August 2023 · Proposed COD January 2027

800 MW

Capacity

2

Components

Solar + Battery

2y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 5m

In Study38%
Queue EntryAug 28, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-01-06

Technology
Solar500 MW · 63%
Battery300 MW · 38%
Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe-Slatt No 1 500kV line

Data Source

LBNL