— Project Summary

Queue ID
BPA-G0919
Capacity
270 MW
Technology
Nuclear
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveNuclearBPALBNL

270 MW generation in Benton, WA · In queue since August 2023 · Proposed COD June 2031

270 MW

Capacity

1

Components

Nuclear

2y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2031

Interconnection Timeline

Total Duration

7y 10m

In Study38%
Queue EntryAug 24, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2031-06-02

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe 500 kV Substation

Data Source

LBNL