90.3 MW generation in Gilliam, OR · In queue since August 2023 · Proposed COD September 2025
90.3 MW
Capacity
1
Components
Wind
2y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 1m
Schedule
7 months past proposed COD
In Study38%
Queue EntryAug 2, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-09-02
Project Details
State
OR
County
Gilliam
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Jones Canyon Substation
Data Source
LBNL
No news available for this project.