BetaActiveSolarBatteryBPALBNL
400 MW hybrid in Deschutes, OR · In queue since July 2023 · Proposed COD November 2033
400 MW
Capacity
2
Components
Solar + Battery
2y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2033
Interconnection Timeline
Total Duration
10y 4m
In Study38%
Queue EntryJul 18, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2033-11-01
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
OR
County
Deschutes
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
LaPine 230kV Substation
Data Source
LBNL
No news available for this project.