— Project Summary

Queue ID
BPA-G0908
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Umatilla, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

500 MW hybrid in Umatilla, OR · In queue since July 2023 · Proposed COD December 2025

500 MW

Capacity

2

Components

Solar + Battery

2y 8m

In Queue

In Progress (unknown study)

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 5m

Schedule

3 months past proposed COD

In Study38%
Queue EntryJul 17, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Technology
Solar300 MW · 60%
Battery200 MW · 40%
Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Longhorn Substation

Data Source

LBNL