BetaActiveBiofuelBatteryBPALBNL
400 MW hybrid in Linn, OR · In queue since June 2023 · Proposed COD December 2030
400 MW
Capacity
2
Components
Biofuel + Battery
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
7y 6m
In Study38%
Queue EntryJun 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-01
Technology
Biofuel200 MW · 50%
Battery200 MW · 50%
Project Details
State
OR
County
Linn
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Santiam-Chemawa No 1 230kV line.
Data Source
LBNL
No news available for this project.