— Project Summary

Queue ID
BPA-G0878
Capacity
160 MW
Technology
Battery
Status
active
Location
Lane, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBiofuelBatteryBPALBNL

160 MW hybrid in Lane, OR · In queue since June 2023 · Proposed COD December 2030

160 MW

Capacity

2

Components

Biofuel + Battery

2y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2030

Interconnection Timeline

Total Duration

7y 6m

In Study38%
Queue EntryJun 30, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2030-12-02

Technology
Biofuel80 MW · 50%
Battery80 MW · 50%
Project Details

State

OR

County

Lane

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Albany-Lebanon No. 1 115kV line

Data Source

LBNL

No news available for this project.