BetaActiveWindBPALBNL
500 MW generation in Lake, OR · In queue since June 2023 · Proposed COD December 2028
500 MW
Capacity
1
Components
Wind
2y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 6m
In Study38%
Queue EntryJun 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Captain Jack Substation
Data Source
LBNL
No news available for this project.