BetaActiveSolarWindBatteryBPALBNL
1,304 MW hybrid in Sherman, OR · In queue since May 2023 · Proposed COD May 2027
1,304 MW
Capacity
3
Components
Solar + Wind + Battery
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryMay 11, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-03
Technology
Solar500 MW · 38%
Wind304 MW · 23%
Battery500 MW · 38%
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Ashe-Marion No 2 500kV line.
Data Source
LBNL
No news available for this project.