— Project Summary

Queue ID
BPA-G0864
Capacity
1304 MW
Technology
Solar+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWindBatteryBPALBNL

1,304 MW hybrid in Sherman, OR · In queue since May 2023 · Proposed COD May 2027

1,304 MW

Capacity

3

Components

Solar + Wind + Battery

2y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryMay 11, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-05-03

Technology
Solar500 MW · 38%
Wind304 MW · 23%
Battery500 MW · 38%
Project Details

State

OR

County

Sherman

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe-Marion No 2 500kV line.

Data Source

LBNL

No news available for this project.