BetaActiveBatteryBPALBNL
400 MW storage in Sherman, OR · In queue since May 2023 · Proposed COD May 2027
400 MW
Capacity
1
Components
Battery
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4 years
In Study38%
Queue EntryMay 11, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-05-03
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
John Day-Marion No 1 500kV line.
Data Source
LBNL
No news available for this project.