BetaActiveWindBPALBNL
500 MW generation in Deschutes, OR · In queue since April 2023 · Proposed COD December 2027
500 MW
Capacity
1
Components
Wind
2y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 8m
In Study38%
Queue EntryApr 25, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Project Details
State
OR
County
Deschutes
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Grizzly-Summer Lake No 1 500kV line
Data Source
LBNL