— Project Summary

Queue ID
BPA-G0858
Capacity
130 MW
Technology
Battery
Status
active
Location
Douglas, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

130 MW storage in Douglas, WA · In queue since April 2023 · Proposed COD December 2026

130 MW

Capacity

1

Components

Battery

2y 11m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 8m

In Study38%
Queue EntryApr 14, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

WA

County

Douglas

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Columbia Substation @ 230kV

Data Source

LBNL

No news available for this project.