BetaActiveSolarBPALBNL
150 MW generation in Columbia, WA · In queue since February 2023 · Proposed COD December 2024
150 MW
Capacity
1
Components
Solar
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
1y 10m
Schedule
15 months past proposed COD
In Study38%
Queue EntryFeb 24, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-30
Project Details
State
WA
County
Columbia
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
PSE's Phalen Gulch 230kV Substation
Data Source
LBNL
No news available for this project.