— Project Summary

Queue ID
BPA-G0843
Capacity
180 MW
Technology
Solar+Battery
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

180 MW hybrid in Klickitat, WA · In queue since February 2023 · Proposed COD June 2026

180 MW

Capacity

2

Components

Solar + Battery

3y 1m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

3y 4m

In Study38%
Queue EntryFeb 22, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-15

Technology
Solar120 MW · 67%
Battery60 MW · 33%
Project Details

State

WA

County

Klickitat

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Horse Heaven - Harvalum No 1 230kV line

Data Source

LBNL

No news available for this project.