BetaActiveSolarBatteryBPALBNL
180 MW hybrid in Klickitat, WA · In queue since February 2023 · Proposed COD June 2026
180 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
3y 4m
In Study38%
Queue EntryFeb 22, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-15
Technology
Solar120 MW · 67%
Battery60 MW · 33%
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Horse Heaven - Harvalum No 1 230kV line
Data Source
LBNL
No news available for this project.