BetaActiveSolarBatteryBPALBNL
600 MW hybrid in Lake, OR · In queue since February 2023 · Proposed COD December 2028
600 MW
Capacity
2
Components
Solar + Battery
3y 1m
In Queue
In Progress (unknown study)
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
5y 10m
In Study38%
Queue EntryFeb 15, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-01
Technology
Solar400 MW · 67%
Battery200 MW · 33%
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Grizzly-Summer Lake #1 or Grizzly-Captain Jack #1 500 kV lines.
Data Source
LBNL
No news available for this project.