— Project Summary

Queue ID
BPA-G0834
Capacity
450 MW
Technology
Solar+Battery
Status
active
Location
Umatilla, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarWindBatteryBPALBNL

450 MW hybrid in Umatilla, OR · In queue since December 2022 · Proposed COD December 2027

450 MW

Capacity

3

Components

Solar + Wind + Battery

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5 years

In Study38%
Queue EntryDec 30, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-01

Technology
Solar175 MW · 39%
Wind175 MW · 39%
Battery100 MW · 22%
Project Details

State

OR

County

Umatilla

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Lower Monumental-McNary No 1 500 kV line through a direct connection to a new 500 kV substation

Data Source

LBNL

No news available for this project.