BetaActiveSolarWindBatteryBPALBNL
450 MW hybrid in Umatilla, OR · In queue since December 2022 · Proposed COD December 2027
450 MW
Capacity
3
Components
Solar + Wind + Battery
3y 3m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5 years
In Study38%
Queue EntryDec 30, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Technology
Solar175 MW · 39%
Wind175 MW · 39%
Battery100 MW · 22%
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Lower Monumental-McNary No 1 500 kV line through a direct connection to a new 500 kV substation
Data Source
LBNL
No news available for this project.