— Project Summary

Queue ID
BPA-G0828
Capacity
100 MW
Technology
Battery
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

100 MW storage in Grant, WA · In queue since December 2022 · Proposed COD December 2026

100 MW

Capacity

1

Components

Battery

3y 3m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryDec 8, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Vantage Substation @ 230kV

Data Source

LBNL

No news available for this project.