BetaActiveSolarBatteryBPALBNL
560 MW hybrid in Klamath, OR · In queue since November 2022 · Proposed COD December 2027
560 MW
Capacity
2
Components
Solar + Battery
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntryNov 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-31
Technology
Solar280 MW · 50%
Battery280 MW · 50%
Project Details
State
OR
County
Klamath
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Primary: Grizzly - Summer Lake No 1 500 kV line. Secondary: Grizzly - Captain Jack No 1 500 kV line.
Data Source
LBNL
No news available for this project.