— Project Summary

Queue ID
BPA-G0822
Capacity
4000 MW
Technology
Solar+Battery
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

4,000 MW hybrid in Benton, WA · In queue since November 2022 · Proposed COD December 2026

4,000 MW

Capacity

2

Components

Solar + Battery

3y 4m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 1m

In Study38%
Queue EntryNov 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Technology
Solar2,000 MW · 50%
Battery2,000 MW · 50%
Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Ashe Substation, or Ashe - Marion No 2 500 kV line, or Ashe - Slatt No 1 500 kV line.

Data Source

LBNL

No news available for this project.