BetaActiveGeothermalBPALBNL
10 MW generation in Cassia, ID · In queue since November 2022 · Proposed COD December 2025
10 MW
Capacity
1
Components
Geothermal
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 1m
Schedule
4 months past proposed COD
In Study38%
Queue EntryNov 14, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Project Details
State
ID
County
Cassia
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA 138KV BRIDGE SUBSTATION
Data Source
LBNL
No news available for this project.