BetaActiveWindBPALBNL
200 MW generation in Douglas, WA · In queue since November 2022 · Proposed COD December 2027
200 MW
Capacity
1
Components
Wind
3y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntryNov 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
WA
County
Douglas
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Columbia-Grand Coulee No 1 230kV line
Data Source
LBNL
No news available for this project.