BetaActivePumped StorageBPALBNL
600 MW storage in Douglas, OR · In queue since September 2022 · Proposed COD December 2030
600 MW
Capacity
1
Components
Pumped Storage
3y 6m
In Queue
In Progress (unknown study)
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
8y 3m
In Study38%
Queue EntrySep 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-12-10
Project Details
State
OR
County
Douglas
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA's Gardiner 230 kV or Tahkenitch 230 kV Substation.
Data Source
LBNL
No news available for this project.