BetaActiveBatteryBPALBNL
650 MW storage in Wasco, OR · In queue since August 2022 · Proposed COD January 2029
650 MW
Capacity
1
Components
Battery
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2029
Interconnection Timeline
Total Duration
6y 5m
In Study38%
Queue EntryAug 18, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2029-01-02
Project Details
State
OR
County
Wasco
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA 500 KV John Day-Marion transmission line.
Data Source
LBNL
No news available for this project.