— Project Summary

Queue ID
BPA-G0791
Capacity
1300 MW
Technology
Solar+Battery
Status
active
Location
Sherman, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

1,300 MW hybrid in Sherman, OR · In queue since August 2022 · Proposed COD December 2028

1,300 MW

Capacity

2

Components

Solar + Battery

3y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 4m

In Study38%
Queue EntryAug 18, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Technology
Solar650 MW · 50%
Battery650 MW · 50%
Project Details

State

OR

County

Sherman

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA 500 KV John Day-Big Eddy 1/2 transmission line.

Data Source

LBNL

No news available for this project.