BetaActiveSolarWindBatteryBPALBNL
600 MW hybrid in Gilliam, OR · In queue since August 2022 · Proposed COD December 2027
600 MW
Capacity
3
Components
Solar + Wind + Battery
3y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 4m
In Study38%
Queue EntryAug 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Technology
Solar200 MW · 33%
Wind300 MW · 50%
Battery100 MW · 17%
Project Details
State
OR
County
Gilliam
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
John Day 500 kV Substation
Data Source
LBNL
No news available for this project.