BetaActiveGasBPALBNL
13 MW generation in Umatilla, OR · In queue since July 2022 · Proposed COD July 2024
13 MW
Capacity
1
Components
Gas
3y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2 years
Schedule
21 months past proposed COD
In Study38%
Queue EntryJul 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-07-01
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Coyote Springs Substation
Data Source
LBNL