— Project Summary

Queue ID
BPA-G0762
Capacity
3 MW
Technology
Solar
Status
active
Location
Lake, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

3 MW generation in Lake, OR · In queue since June 2022 · Proposed COD December 2024

3 MW

Capacity

1

Components

Solar

3y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 6m

Schedule

15 months past proposed COD

In Study38%
Queue EntryJun 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

OR

County

Lake

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

LaPine Substation

Data Source

LBNL