BetaActiveSolarBPALBNL
3 MW generation in Lake, OR · In queue since June 2022 · Proposed COD December 2024
3 MW
Capacity
1
Components
Solar
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 6m
Schedule
15 months past proposed COD
In Study38%
Queue EntryJun 28, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
OR
County
Lake
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
LaPine Substation
Data Source
LBNL
No news available for this project.