— Project Summary

Queue ID
BPA-G0761
Capacity
290 MW
Technology
Wind
Status
active
Location
Grant, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindBPALBNL

290 MW generation in Grant, WA · In queue since June 2022 · Proposed COD June 2026

290 MW

Capacity

1

Components

Wind

3y 9m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4 years

In Study38%
Queue EntryJun 23, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-06-30

Project Details

State

WA

County

Grant

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

TBD

Data Source

LBNL

No news available for this project.