1,365 MW hybrid in Jefferson, OR · In queue since June 2022 · Proposed COD December 2025
1,365 MW
Capacity
3
Components
Solar + Gas + Battery
3y 9m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 6m
Schedule
3 months past proposed COD
In Study38%
Queue EntryJun 16, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Technology
Solar365 MW · 27%
Gas400 MW · 29%
Battery600 MW · 44%
Project Details
State
OR
County
Jefferson
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
5-mile 500kV Gen Tie to Grizzly 500 kV Substation
Data Source
LBNL
No news available for this project.