— Project Summary

Queue ID
BPA-G0745
Capacity
200 MW
Technology
Solar+Battery
Status
active
Location
Adams, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryBPALBNL

200 MW hybrid in Adams, WA · In queue since May 2022 · Proposed COD December 2026

200 MW

Capacity

2

Components

Solar + Battery

3y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntryMay 25, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Technology
Solar100 MW · 50%
Battery100 MW · 50%
Project Details

State

WA

County

Adams

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Hatton tap to Connell tap

Data Source

LBNL

No news available for this project.