BetaActiveSolarBatteryBPALBNL
85 MW hybrid in Umatilla, OR · In queue since April 2022 · Proposed COD December 2025
85 MW
Capacity
2
Components
Solar + Battery
3y 11m
In Queue
In Progress (unknown study)
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 8m
Schedule
4 months past proposed COD
In Study38%
Queue EntryApr 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-01
Technology
Solar60 MW · 71%
Battery25 MW · 29%
Project Details
State
OR
County
Umatilla
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA_x0019_s Morrow Flat 230 kV
Data Source
LBNL
No news available for this project.