BetaActiveBatteryBPALBNL
20 MW storage in Benton, WA · In queue since March 2022 · Proposed COD November 2024
20 MW
Capacity
1
Components
Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 8m
Schedule
17 months past proposed COD
In Study38%
Queue EntryMar 15, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-15
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
New 230 kV Substation that will tap the Franklin-McNary 230kV Transmission Line.