BetaActiveSolarBatteryBPALBNL
400 MW hybrid in Benton, WA · In queue since March 2022 · Proposed COD April 2027
400 MW
Capacity
2
Components
Solar + Battery
4 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 1m
In Study38%
Queue EntryMar 11, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-04-15
Technology
Solar200 MW · 50%
Battery200 MW · 50%
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Wautoma 500 kV
Data Source
LBNL
No news available for this project.