BetaActiveBatteryBPALBNL
600 MW storage in Coos, OR · In queue since January 2022 · Proposed COD December 2027
600 MW
Capacity
1
Components
Battery
4y 2m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
5y 11m
In Study38%
Queue EntryJan 26, 2022
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-10
Project Details
State
OR
County
Coos
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Fairview 230 kV Substation
Data Source
LBNL