— Project Summary

Queue ID
BPA-G0725
Capacity
600 MW
Technology
Battery
Status
active
Location
Coos, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

600 MW storage in Coos, OR · In queue since January 2022 · Proposed COD December 2027

600 MW

Capacity

1

Components

Battery

4y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

5y 11m

In Study38%
Queue EntryJan 26, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-10

Project Details

State

OR

County

Coos

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Fairview 230 kV Substation

Data Source

LBNL