— Project Summary

Queue ID
BPA-G0724
Capacity
600 MW
Technology
Battery
Status
active
Location
Curry, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

600 MW storage in Curry, OR · In queue since January 2022 · Proposed COD December 2026

600 MW

Capacity

1

Components

Battery

4y 2m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 11m

In Study38%
Queue EntryJan 26, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-10

Project Details

State

OR

County

Curry

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Fairview-Rogue No 1 230 KV line.

Data Source

LBNL

No news available for this project.