BetaActiveWindBPALBNL
13.6 MW generation in Benton, WA · In queue since December 2021 · Proposed COD November 2024
13.6 MW
Capacity
1
Components
Wind
4y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 11m
Schedule
17 months past proposed COD
Facilities Study50%
Queue EntryDec 22, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-11-15
Project Details
State
WA
County
Benton
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Franklin - McNary 230 kV line, at the new Bofer Canyon Substation
Data Source
LBNL
No news available for this project.