— Project Summary

Queue ID
BPA-G0721
Capacity
13.6 MW
Technology
Wind
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveWindBPALBNL

13.6 MW generation in Benton, WA · In queue since December 2021 · Proposed COD November 2024

13.6 MW

Capacity

1

Components

Wind

4y 3m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 11m

Schedule

17 months past proposed COD

Facilities Study50%
Queue EntryDec 22, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-11-15

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Franklin - McNary 230 kV line, at the new Bofer Canyon Substation

Data Source

LBNL

No news available for this project.