— Project Summary

Queue ID
BPA-G0717
Capacity
75 MW
Technology
Battery
Status
active
Location
Klickitat, WA
Region
West
Developer
IA Status
Facility Study

BetaActiveBatteryBPALBNL

75 MW storage in Klickitat, WA · In queue since December 2021 · Proposed COD September 2024

75 MW

Capacity

1

Components

Battery

4y 3m

In Queue

Facility Study

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 9m

Schedule

19 months past proposed COD

Facilities Study50%
Queue EntryDec 7, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-09-01

Project Details

State

WA

County

Klickitat

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Rock Creek Substation

Data Source

LBNL

No news available for this project.