BetaActiveBatteryBPALBNL
75 MW storage in Klickitat, WA · In queue since December 2021 · Proposed COD September 2024
75 MW
Capacity
1
Components
Battery
4y 3m
In Queue
Facility Study
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 9m
Schedule
19 months past proposed COD
Facilities Study50%
Queue EntryDec 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Rock Creek Substation
Data Source
LBNL
No news available for this project.