BetaActiveBiofuelBPALBNL
1.6 MW generation in Flathead, MT · In queue since November 2021 · Proposed COD September 2022
1.6 MW
Capacity
1
Components
Biofuel
4y 4m
In Queue
In Progress (unknown study)
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
10 months
Schedule
43 months past proposed COD
In Study38%
Queue EntryNov 2, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-09-01
Project Details
State
MT
County
Flathead
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Flathead Substation
Data Source
LBNL
No news available for this project.