— Project Summary

Queue ID
BPA-G0709
Capacity
41 MW
Technology
Battery
Status
active
Location
Gilliam, OR
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryBPALBNL

41 MW storage in Gilliam, OR · In queue since October 2021 · Proposed COD December 2023

41 MW

Capacity

1

Components

Battery

4y 5m

In Queue

In Progress (unknown study)

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

2y 2m

Schedule

28 months past proposed COD

In Study38%
Queue EntryOct 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

Project Details

State

OR

County

Gilliam

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

BPA's Slatt 230 kV Substation

Data Source

LBNL