BetaActiveBatteryBPALBNL
60 MW storage in Morrow, OR · In queue since October 2021 · Proposed COD December 2023
60 MW
Capacity
1
Components
Battery
4y 5m
In Queue
In Progress (unknown study)
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
2y 2m
Schedule
28 months past proposed COD
In Study38%
Queue EntryOct 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-12-01
Project Details
State
OR
County
Morrow
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
BPA_x0019_s Boardman _x0013_ Alkali 115 kV transmission line.
Data Source
LBNL