— Project Summary

Queue ID
BPA-G0705
Capacity
60 MW
Technology
Solar
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

60 MW generation in Benton, WA · In queue since September 2021 · Proposed COD December 2024

60 MW

Capacity

1

Components

Solar

4y 6m

In Queue

In Progress (unknown study)

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 3m

Schedule

15 months past proposed COD

In Study38%
Queue EntrySep 24, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Plymouth Tap 115 kV

Data Source

LBNL

No news available for this project.