BetaActiveSolarBPALBNL
900 MW generation in Sherman, OR · In queue since August 2021 · Proposed COD December 2024
900 MW
Capacity
1
Components
Solar
4y 7m
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 4m
Schedule
15 months past proposed COD
In Study38%
Queue EntryAug 25, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
OR
County
Sherman
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
45.371967, -120.707373 - Grass valley Sherman County OR
Data Source
LBNL
No news available for this project.