— Project Summary

Queue ID
BPA-G0686
Capacity
127.5 MW
Technology
Solar
Status
active
Location
Benton, WA
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBPALBNL

127.5 MW generation in Benton, WA · In queue since August 2021 · Proposed COD July 2028

127.5 MW

Capacity

1

Components

Solar

4y 7m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

6y 11m

In Study38%
Queue EntryAug 13, 2021

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-07-03

Project Details

State

WA

County

Benton

Region

West

Developer

Utility

Bonneville Power Administration

Entity

BPA

Point of Interconnection

Benton No 2 115 kV line.

Data Source

LBNL