BetaActiveSolarBatteryBPALBNL
2,000 MW hybrid in Marion, OR · In queue since July 2021 · Proposed COD December 2026
2,000 MW
Capacity
2
Components
Solar + Battery
4y 8m
In Queue
In Progress (unknown study)
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
5y 5m
In Study38%
Queue EntryJul 7, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Technology
Solar1,000 MW · 50%
Battery1,000 MW · 50%
Project Details
State
OR
County
Marion
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Buckley - Marion No 1 500 kV line
Data Source
LBNL
No news available for this project.