BetaActiveSolarBatteryBPALBNL
250 MW hybrid in Klickitat, WA · In queue since March 2021 · Proposed COD September 2024
250 MW
Capacity
2
Components
Solar + Battery
5 years
In Queue
In Progress (unknown study)
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 6m
Schedule
19 months past proposed COD
In Study38%
Queue EntryMar 29, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-09-01
Technology
Solar125 MW · 50%
Battery125 MW · 50%
Project Details
State
WA
County
Klickitat
Region
West
Developer
—
Utility
Bonneville Power Administration
Entity
BPA
Point of Interconnection
Spring Creek Substation 230 kV
Data Source
LBNL